This week in South Florida real estate.
The freshest development, infrastructure, retail, school, and market activity across Miami-Dade County, summarized from public reporting and official sources by our team and linked to the original coverage. Updated weekly. Last updated October 9, 2026.
The latest, newest first.
Want the running history for a specific area? Each county hub keeps its own tracked timeline: Miami-Dade County. Community pages on the interactive map carry the same tracked sections for the neighborhoods we cover.
- October 7, 2026DevelopmentMiami-Dade County
Casa Bella Residences opens at 1400 Biscayne Boulevard with closings underway
The 56 story, 319 residence condominium tower by Related Group and Alta Developers has begun closings, with more than 90 percent of homes reported under contract. It is the first residential project from B&B Italia and was designed by Arquitectonica.
Source: Florida YIMBY - October 6, 2026DevelopmentMiami-Dade County
Swire Properties breaks ground on the Residences at Mandarin Oriental on Brickell Key
Work has started on a two tower project on the south end of Brickell Key, with a 66 story tower of 228 residences and a 33 story tower of 98 residences plus a 121 room hotel. Delivery is scheduled for 2030, following the April demolition of the former hotel.
Source: Florida YIMBY - October 4, 2026DevelopmentMiami-Dade County
Sweetbird North breaks ground at 95 NE 40th Street in the Design District
An eight story office and retail building of roughly 120,500 square feet, including about 92,000 square feet of office and 22,500 square feet of retail, started construction on September 30. Miami Design District Associates and Raycliff Capital are the partners, with completion expected in early 2028.
Source: Florida YIMBY - October 2, 2026DevelopmentMiami-Dade County
Related Urban closes 167.1 million dollar construction financing for Gallery at Lummus Parc downtown
Related Urban Development Group closed 167.1 million dollars in construction financing for Gallery at Lummus Parc at 395 NW First St., a two tower affordable rental project already under construction. Phase one will have 257 units, about 80 percent income restricted, and phase two adds 182 more in towers of 27 and 30 stories. Phase one is targeted for 2028.
Source: Florida YIMBY - September 30, 2026DevelopmentMiami-Dade County
Ken Griffin closes 1.1 billion dollar purchase of the Mana Wynwood assemblage for a planned Carnegie Mellon campus
Ken Griffin closed an all cash purchase of Moishe Mana's roughly 35 acre Wynwood land assemblage for about 1.1 billion dollars. The site is planned to become a Carnegie Mellon University Miami campus, with enrollment targeted for 2028 pending approvals.
Source: The Real Deal - September 22, 2026DevelopmentMiami-Dade County
Crescent Heights plans NEMA, two towers with 1,030 apartments at 3180 Biscayne Boulevard in Edgewater
Crescent Heights filed plans for NEMA, a two tower mixed use project with 1,030 apartments on a 2.63 acre assemblage at 3180 Biscayne Blvd. in Miami's Edgewater area. A 49 story east tower would hold 618 market rate units and a west tower 412 income restricted units for households earning up to 120 percent of area median income, under the Live Local Act, with about 105,000 square feet of commercial space and 941 parking spaces. The plan went before Miami's Urban Development Review Board on Sept. 16.
Source: Florida YIMBY - September 9, 2026DevelopmentMiami-Dade County
HTG advances the 328 unit, 126.4 million dollar Lakeview at Naranja on South Dixie Highway in Homestead
Housing Trust Group is moving ahead with Lakeview at Naranja, an eight story, two phase income restricted community at 27501 and 27525 South Dixie Highway. Phase one would hold 203 apartments and 264 parking spaces and phase two 125 apartments and 207 spaces, with 11,466 square feet of commercial space and units reserved for households earning 30 to 80 percent of area median income. The Naranja Lakes CRA, which bought the site for 12.62 million dollars in 2025, sold it to HTG for a nominal sum and extended a 7 million dollar loan; HTG will also fund 3.3 million dollars in lakefront and pedestrian improvements.
Source: Florida YIMBY - September 9, 2026DevelopmentMiami-Dade County
The Lincoln in Coconut Grove lands a 58 million dollar construction loan with sales past 40 percent
LORE Development Group and Element Development closed a 58 million dollar senior construction loan from SME Capital, arranged by Berkadia, for The Lincoln, an eight story, 48 unit condominium at 2650 Lincoln Avenue. The loan carries a 30 month term with two six month extensions, and the developers said sales surpassed 40 percent at a recent groundbreaking. Units range from one to four bedrooms, including six penthouses up to 3,633 square feet, with completion scheduled for the third quarter of 2028.
Source: Florida YIMBY - September 8, 2026InfrastructureMiami-Dade County
Four of six arches now closed on the I-395 Signature Bridge as the 866 million dollar corridor rebuild targets late 2029
A September 2 project update reports arches 1, 2, 4 and 5 of the 1,025 foot Signature Bridge over Northeast 2nd Avenue and Biscayne Boulevard are closed, with crews forming the remaining cast in place elements on arches 3 and 6 and building the westbound superstructure. The largest arch rises about 325 feet and spans 650 feet. The broader I-395, State Road 836 and I-95 reconstruction covers about 1.4 miles of I-395 with three through lanes each way plus a double decked 836 section, at an official cost of 866 million dollars and a late 2029 completion target.
Source: Florida YIMBY - September 1, 2026MarketMiami-Dade County
Terra lands a 245 million dollar bridge loan for the 578 unit first phase of Upland Park in Sweetwater
Terra secured a 245 million dollar bridge loan from SCALE Lending for Phase 1A of Upland Park, its 47 acre mixed use project next to the Dolphin Station park and ride terminal at 1455 NW 121st Avenue in West Miami-Dade. The 578 apartment phase opened this summer and was more than 60 percent leased within 90 days, with remaining construction due to finish in October 2026. A second phase of 484 apartments is planned to start later this year, and the full master plan calls for more than 2,000 units plus hotel, retail and office space.
Source: Florida YIMBY - August 20, 2026DevelopmentMiami-Dade County
Pre-application filed for a 112 unit age restricted apartment building in Naranja
Tower Road Gardens, an affiliate of Centennial Management, submitted a pre-application for Villa Valencia, an eight story building with 112 one and two bedroom apartments and 59 parking spaces near Southwest 268th Street and Southwest 149th Avenue. Gallo Herbert Architects designed the age restricted community, which is not being filed under the Live Local Act. Miami-Dade counts housing as affordable at or below 120 percent of area median income, with the county median income listed at 87,200 dollars as of May 2025.
Source: Florida YIMBY - August 20, 2026CivicMiami-Dade County
Court clears a November referendum on a 27.6 acre Virginia Key marina lease
A Miami-Dade Circuit Court judge dismissed a challenge seeking to keep the Rickenbacker and Marine Stadium marina lease off the November 3 ballot. City of Miami voters will now decide on a 45 year lease with two 15 year renewal options for roughly 27.62 acres of city owned waterfront, where a joint venture of RCI Group and Suntex Marinas proposes about 80 million dollars in privately funded work covering boat storage, restaurants, retail and public parking. The lease terms call for minimum guaranteed rent of 2.2 million dollars a year plus six percent of gross revenues.
Source: Florida YIMBY - August 18, 2026DevelopmentMiami-Dade County
Casa Princeton final phase to add 162 apartments on Southwest 248th Street in Homestead
Coral Gables based Aconcagua Developers is advancing the third and final phase of Casa Princeton, an eight story building with 162 one and two bedroom apartments averaging roughly 795 square feet across about 163,807 square feet of new construction. A 35 million dollar construction loan backs the phase, and the developer paid 3.6 million dollars for the 2.7 acre site in 2024. Completion is targeted for 2027 or 2028, bringing the full community to 374 units.
Source: Florida YIMBY - August 17, 2026DevelopmentMiami-Dade County
Solara Village pre-application proposes 200 income restricted apartments on Northwest 79th Street
MHG Developers of Boca Raton filed a pre-application for Solara Village, an eight story building with 200 one and two bedroom apartments ranging from about 490 to 800 square feet, plus 2,000 square feet of retail and 213 parking spaces. The firm has the undeveloped 2.84 acre site under contract, and Gallo Herbert Architects is the designer. Income parameters were not disclosed at filing, and Miami-Dade defines affordable housing as reaching households at or below 140 percent of area median income.
Source: Florida YIMBY - August 16, 2026DevelopmentMiami-Dade County
Foundation work begins on the 33 story, 282 unit 1600 Edgewater tower in Miami
Crews are drilling and excavating at 1600 Northeast 2nd Avenue, where Sabet Group is building a roughly 384 foot tower designed by Kobi Karp with 282 rental units, 9,519 square feet of commercial space and 352 parking spaces. The unit mix includes 262 market rate residences and 20 units reserved at or below 60 percent of area median income, with a rooftop pool and restaurant planned. Site preparation, foundation and vertical construction permits are approved while the master permit covering nearly 500,000 square feet and more than 93 million dollars in value remains under review.
Source: Florida YIMBY - August 16, 2026MarketMiami-Dade County
Metro Parc in Hialeah lands 226.5 million dollars in refinancing at roughly half leased
Baron Property Group refinanced the 559 unit, two tower Metro Parc at 952 East 26th Street, replacing a 148 million dollar construction loan with 125 million dollars in senior debt from Madison Realty Capital and 101.5 million dollars in preferred equity from Yellowstone Real Estate. The 10 story property delivered in 2025, includes more than 15,000 square feet of ground floor retail and is nearing 50 percent leased. The 661 unit Metro Parc North second phase topped out this year and is due for completion in late 2027.
Source: Florida YIMBY - August 10, 2026DevelopmentMiami-Dade County
Master permit filed for a 45 story, 667 unit first tower at 3333 Biscayne Boulevard
Beitel Group filed a master construction permit for the first of three towers on a 2.91 acre Edgewater block, calling for 45 stories, 667 residences, structured parking and 7,408 square feet of ground floor retail with John Moriarty and Associates as general contractor. Demolition and tree removal permits are approved and site work has begun, while piling, master permit and phased vertical construction filings remain under review. Four crane applications list an operating window from December 1, 2026 through July 31, 2028.
Source: Florida YIMBY - July 16, 2026DevelopmentMiami-Dade County
Miami civic center at Freedom Park tops off ahead of a spring 2028 target
Construction workers topped off the eight story, 257,000 square foot Miami civic center at Miami Freedom Park on July 10, and the city confirmed it received the construction permit on July 1. Adler Development is the developer and Moss Construction the general contractor, with completion targeted for spring 2028 and a separate 20 million dollar pedestrian bridge to the Metrorail station under construction. The building would consolidate city administrative functions now split between a downtown office building and City Hall at 3500 Pan American Drive.
Source: The Real Deal South Florida - July 16, 2026MarketMiami-Dade County
A 30 million dollar penthouse contract sets a Miami River price record
KAR Properties and Fortune International Group put a penthouse at their Faena branded Miami River project under contract for 30 million dollars, roughly 3,700 dollars per square foot, which The Real Deal reports as a record for the area on both price and price per square foot. The duplex covers 8,200 square feet of interior space plus 7,000 square feet outdoors. The 440 unit, two tower project at 90 Southwest Third Street has not started construction.
Source: The Real Deal South Florida - July 16, 2026Retail & DiningMiami-Dade County
Coconut Grove retail asking rents topped 110 dollars per square foot in the second quarter
Colliers data cited by The Real Deal put average direct asking retail rents in Coconut Grove above 110 dollars per square foot in the second quarter of 2026, among the highest of any Miami-Dade submarket and more than double the 45.50 dollar average of a decade ago. Brokers attribute the increase to limited available retail inventory against rising leasing demand. Several long running restaurant tenants have closed or relocated as leases reset at higher rates.
Source: The Real Deal South Florida - July 15, 2026CivicMiami-Dade County
County advances a same day permitting ordinance for some residential applications
Miami-Dade's Policy Council advanced an ordinance from Chairman Anthony Rodriguez that would require the county to run a same day permitting program for eligible residential applications, with financial penalties on the county itself when it misses those deadlines because of county delay. The measure would also require a performance report every six months. It is scheduled for final commission action on July 21 and has not been adopted.
Source: Miami Today - July 15, 2026Parks & AmenitiesMiami-Dade County
County committee scheduled to vote on a 3.5 million dollar purchase of 10 acres in the South Dade Wetlands
Miami-Dade is moving toward buying 10 acres inside the South Dade Wetlands Project at Southwest 344th Street and Southwest 169th Avenue for 3.5 million dollars from the estate of Rachel M. Noto. Funding would come from the Environmentally Endangered Lands Program, which held a 12.5 million dollar balance before the purchase, and the county intends to seek a 10 percent reimbursement from the Florida Department of Environmental Protection. The Recreation, Tourism and Resiliency Committee was scheduled to vote, so this is an agenda item rather than a completed acquisition.
Source: Miami Today - July 15, 2026DevelopmentMiami-Dade County
Foundation pour finished at Twenty Sixth & 2nd in Wynwood
PMG and LNDMRK Development completed the foundation pour for Twenty Sixth & 2nd Wynwood Residences, an eight story mixed use building at 2600 NW 2nd Avenue, and a tower crane has since been erected. The project will deliver 233 finished and furnished studio and one bedroom residences plus about 26,000 square feet of ground floor retail. Cube 3 designed it, John Moriarty & Associates is the builder, and completion is anticipated in the second quarter of 2028.
Source: Florida YIMBY - July 14, 2026DevelopmentMiami-Dade County
West Perrine apartment project lands a 43 million dollar construction loan
Perrine Estates LLC, an affiliate of Monceau Realty, secured a 43 million dollar construction loan for a 192 unit apartment project on a vacant 1.47 acre parcel at Banyan Street and Homestead Avenue in West Perrine. About 12.5 percent of the units are set aside as county workforce housing, which Miami-Dade defines as 60 to 140 percent of area median income. The plan also carries roughly 2,000 square feet of retail.
Source: Florida YIMBY - July 13, 2026DevelopmentMiami-Dade County
County zoning board clears a rezoning for 300 student beds near the university
The Miami-Dade Community Zoning Appeals Board approved a rezoning of a 2.89 acre site at 6280 SW 57th Avenue, clearing the way for Vox on Red, a six story, 117 unit project holding about 300 student beds. Treo Group affiliate TTG 57 LLC bought the site for 10.2 million dollars in 2024, and a 1930s house on the property is slated to be folded into the plan. The developer still needs permits from several agencies before work can begin.
Source: Florida YIMBY - July 12, 2026DevelopmentMiami-Dade County
Allapattah tower plan would set 40 percent of units at 120 percent of AMI
Developers Cipres and Medio Tiempo revealed plans for The Pattah, a 20 story, 280 unit building with about 310,000 square feet of construction and 9,300 square feet of ground floor retail near 1219 NW 35th Street. Of the units, 112, or 40 percent, would serve households earning up to 120 percent of area median income. The team assembled the 0.73 acre, four parcel site for 3.48 million dollars between 2019 and 2025 and had not yet filed a formal application as of publication.
Source: Florida YIMBY
Summaries reflect public reporting and official sources linked above as of the dates shown. Project details, timelines, and approvals can change. Nothing here is investment advice or a prediction for any specific property.
Momentum also tracks weekly development news for Northeast Florida, Orlando Metro, Tampa Bay.
